Clements University Hospital
See All ProjectsProject Overview:
TDIndustries played a prominent role as a design-assist specialty contractor to mitigate the complexities that accompanied a project of this magnitude. TD was responsible for the total mechanical work for HVAC, plumbing and medical gas systems. Construction began in August 2010, and the facility was fully operational on December 6, 2014, wrapping up ahead of schedule and on budget.
Market
- Healthcare
Location
Dallas, Texas
Services Provided
- Engineering
- Construction
- Process Piping
Project Size
1.3 million square feet
Project Complexity
Key factors in overcoming the project’s challenges involved construction innovations, prefabrication by TD’s manufacturing shop and Lean processes. For the work on the Clements University Hospital construction, TD won a TEXO Distinguished Building Award and the ABC National Excellence in Construction First Place Eagle Award with Productivity Award distinction.